Dunn Lake Road Realignment

Completed Works:  The crews completed this weeks planned activities to clear from Sta. 73+45 to Sta 92+03. A Brushing crew is following behind to take down the remaining vegetation coverage. 1 traffic control crew onsite. 

 Bird sweeps have started from Sta. 92+03 to Sta.110+61

 Planned activities for next week: Continue clearing from Sta 92+03 to 110+61.  Track chipper being brought to site to assist in the larger areas requiring clearing at the SRG office,  beginning Tuesday June 30th. There will be 2 rock trucks that will be crossing Dunn Lake Road. Traffic Control Crew will be added to ensure the safety of vehicles traveling on Dunn Lake Road. The hauling is planned to last 1 week. 

Planned shut down for the 3rd of July, in lieu of Canada Day.

 

Thank you,

Brittany Simpson
SRG Project Liasion

 

For Previous Maps and Diagrams, please see Dunn Lake Road Realignment

15LS0646 63-65

15LS0646 COMPILED LOT 64

15LS0646 COMPILED LOT 67

15LS0646 COMPILED LOT 73

15LS0646 COMPILED LOT 77 242

Download the road survey plans:

76566- compiled road replacement 
15LS0646 63-65

15LS0646 COMPILED LOT 64

15LS0646 COMPILED LOT 67

15LS0646 COMPILED LOT 73

15LS0646 COMPILED LOT 77 242