Dunn Lake Road Realignment

Completed Works:  

The crews have completed working the area through the community. There was a mechanical brusher that was brought to site to assist in the ground clearing for this week and has completed all the work they were able to do and have demobilized today, July 24th.

Planned activities for next week:

Complete the clearing in the final section from Sta 18+000 to Sta 18+700. The crew will be working through areas between the SRG office and the community to clean up some of the areas previously skipped due to birds nests. Traffic control is to be expected between SRG and the community.

 

Environmental:

Bird nest sweeps are scheduled this weekend, and extending into Monday, Tuesday and Wednesday to support the areas that were previously buffered due to active nests. No other concerns have been noted at this time.

 

Thank you,

 

Brittany Simpson